By Jacob van Winkle
This is the third article in a series about the Ameritania sign. The first, Remove Illegal Sign, ran in May. The second, The Phone Call in Lieu, ran in July.
At 7:37 on the morning of Monday, June 3, 2024, the Chief Plan Examiner of the Department of Buildings’ Special Enforcement Team sent a two-line email to the architect for the LED advertising sign on the Ameritania Hotel at Broadway and 54th Street.
“Objection #1 is resolved. Please provide the floor plans with the room layouts for each foor.”
Objection 1 was this, written by the same unit thirty-three days earlier on the DOB’s own audit sheet:
“The illuminated sign projects or reflect on residences of premise and the premise on the opposite side of street at 229 West 54th Street (AKA 1717 Broadway). Each are hotels defined as a multiple dwelling. This is contrary to ZR 32-64.”
ZR 32-64 is the zoning rule that protects homes from illuminated signs. It is the rule Assembly Member Linda Rosenthal told the DOB it should be applying in 2019, in the letter the DOB answered by telephone so that nothing would be written down. On May 1, 2024, five years after that phone call, the DOB’s own enforcement unit applied the rule to this sign and found the sign contrary to it. On May 6 and May 7 it issued formal Intents to Revoke, notices that it meant to take the permits away.
The finding stood for thirty-three days.
Six days
What happened in between is in the DOB’s own emails. It did not produce them when we asked for the sign’s file. It produced them on appeal, on September 17, 2026.
On May 28, 2024, the DOB Special Enforcement Team was still objecting. Its morning email to the owner’s architect, on Objection 1: “Complaints have been recieved from 1752 BROADWAY a Mixed Residential & Commercial Building.” That afternoon the architect wrote back with two questions. Where could the standard referenced in ZR 32-64 “be located”? And “how any illuminated advertising sign gets built in the C6-7 district (Which also encompasses Times Sqaure) if ZR 32-64 applies to neighboring buildings and buildings within sight of the sign?” C6-7 is the zoning district the sign sits in.
Six days later: “Objection #1 is resolved.”
Nothing in the produced record answers the architect’s questions. Nothing explains the resolution. The record shows no inspection, no measurement, no memo. The DOB withheld two internal emails from this file as deliberative material and did not say what dates they carry.
What kept the file open
The audit did not close in June 2024. It stayed open for two more years on other questions, among them the location of an apartment on the hotel’s seventh floor, which the hotel’s own certificate of occupancy lists and which the owner’s architect was still looking for a floor plan of in December 2025. The finding about light into homes was never mentioned again.
Through all of it the sign ran around the clock, into roughly 180 apartments across the street. In May 2026 the head of the DOB’s sign unit wrote to the sign’s operator that it was “still very bright” after ten at night. We have asked the DOB eleven times under the Freedom of Information Law for any record of an inspector standing on 54th Street after dark, or any measurement of the light. Nothing it has produced contains one.
The permit is changed to match the sign
In June 2026 the DOB resolved the oldest problem with this sign.
Since 2017 the sign’s permit had allowed one type of illumination: Direct. Since 2017 the sign had flashed, which is a different type. A DOB inspector wrote that down on a checklist in 2020. In June 2026 the Special Enforcement Team’s comments to the architect read: “Please revise the PW-1 sign characteristics to change the type of illumination from direct to flashing.” The PW-1 is the permit application. On June 22 the architect confirmed: “we have corrected the sign characteristics from ‘Direct Illumination’ to ‘Flashing Illumination.’”
On August 6, 2026, the DOB approved the amendment. The applicant’s note on it: “PAA herewith filed to answer audit objections.” A PAA is a post-approval amendment, the form for changing a permit after it has been issued. On August 11 the Special Enforcement Team wrote: “SET accepted the audit in DOB NOW. SET has no further action.” DOB NOW is the DOB’s online filing system.
On August 27 the Commissioner of Buildings answered a letter Council Member Gale Brewer had sent in May asking the DOB to enforce the law against a sign that “projects intense lights into the apartments of the adjacent residential buildings.” He wrote that the audit “identified several technical issues” and that “there was no basis for revoking the permit.” He wrote that the amendment “remains under review.” His own enforcement team had closed it sixteen days earlier. He did not mention the rule about light into homes.
Thirty days
On September 10, Community Board 5 voted 37 to 1 and wrote the Commissioner that the DOB’s information to the board had “not been complete, clear, accurate, or fully responsive.” On September 11, Council Member Brewer wrote again with two questions: does the sign comply with ZR 32-64, and when did the DOB last inspect it while lit. She asked for an answer within thirty days.
October 9, 5:43 PM. The DOB’s Director of Intergovernmental Affairs emails the Council Member’s office. The email does not mention ZR 32-64. It says the zoning sections it cites “do not impose limitations on the size, brightness or height of such signs,” and attaches a Council bill on residential floodlights that exempts “part of a lawful illuminated sign” by name. The same official wrote to DOB colleagues in July 2019 that “the code does not have a restriction on brightness.” The Zoning Resolution has directed the DOB to adopt one by rule since 2001.
October 9, 6:11 PM, by the DOB’s own data: the second permit’s audit status changes from “15 Day Notice of Intent to Revoke” to “Audit Status: Accepted.” The seventh-floor apartment is not mentioned again in any record we have.
October 11. Brewer’s thirty days run out. Her office told us on October 14 that it had received no response; it located the October 9 email the next day. We received a copy on November 9 from Council Member Wilson’s office. The DOB had resolved the architect’s objection in six days.
October 12. The owner files a new amendment on that permit. The note: “PAA herewith filed to update drawings as per Audit.” The documents attached, as the public portal lists them: an asbestos form and a housing form.
October 29. Approved.
What we still do not know
Why the DOB resolved Objection 1 on June 3, 2024.
What is in the two emails it withheld.
What the drawings approved on October 29 show.
Whether anyone from the DOB has ever looked at this sign after dark.
On October 30 we filed a records request for the complete October filing, the approved drawings, the examiner’s comments, and every record by which the second permit’s audit was closed, including all communications between the DOB and the owner’s representatives since May 1, 2024.
Where the question goes now
For nine years every letter about this sign has gone to the DOB: from residents, a State Assembly Member, two Council Members, and a Community Board. The DOB has answered by phone, or late, or not at all, and nothing happened when it did not answer.
There is a reason. The Commissioner of Buildings is appointed by the Mayor and answers to the Mayor. A Council Member’s letter carries no deadline the law enforces. Neither does a Community Board’s. The bodies that can require an answer are the ones this sign has never been put in front of.
So this week we wrote a different kind of letter. We asked the Manhattan Borough Commissioner for a written determination: whether the sign, as the DOB approved it on August 6 and October 29, complies with ZR 32-64, and on what basis the Special Enforcement Team resolved its own Objection 1 on June 3, 2024. A determination is not a courtesy reply. It is a decision the City Charter lets a resident appeal to the Board of Standards and Appeals, which is not the DOB. If the DOB answers, the answer can go to the Board. If it does not, the DOB’s own formal process for a written determination, which a lawyer or licensed architect has to file for us, is open, and we intend to use it.
Our lawsuit against the DOB over its withheld records is on the court’s calendar for November 16. The City’s answer is due the week before.
Somewhere in the DOB’s files is the reason this sign became acceptable on June 3, 2024. We intend to read it. The sign was on at 7:37 that morning. It is on now.
Every document quoted above is a PDF obtained from the Department of Buildings under the Freedom of Information Law and is linked in the text. Reporters: we will send you all of it.
Correction, November 10, 2026: an earlier version of this article said the Department of Buildings did not respond to Council Member Brewer’s September 11 letter within thirty days. The Department’s Director of Intergovernmental Affairs emailed the Council Member’s office on October 9 at 5:43 PM. The Council Member’s office told us on October 14 that it had received no response and located the email on October 15. We obtained a copy on November 9. The email is linked above; it does not mention ZR 32-64. The text has been revised.
Jacob van Winkle is Treasurer of the West 50s Neighborhood Association. jacobnyc54@gmail.com
Authored by Jacob van Winkle, Treasurer, West 50s Neighborhood Association.